Question: 11 of 143

What does PDCA mean?

A) Plan-Do-Check-Act
B) Prepare-Do-Cost-Act
C) Plan-Do-Control-Action
D) Prepare-Do-Control-Action
Asked by: Interview Candidate | Asked on: Dec 8th, 2005
Showing Answers 1 - 7 of 7 Answers
deven

Answered On : Dec 8th, 2005

PLAN DO CHECK ACT

  
Login to rate this answer.
Brunda

Answered On : Dec 9th, 2005

Plan
Do
Check
Act

  
Login to rate this answer.
Basivi Reddy

Answered On : Jan 31st, 2006

Plan: Plan every activity in a project with proper analysis and considerations for risks and other constraints

Do : Work on the activity as per the plan and complete it

Check: Check the work you have done with Quality Standards and correct the anomolies

Act : Do the root cause analysis and correct the process to prevent the occurance of errors in future.

  
Login to rate this answer.
baskie

Answered On : May 7th, 2008

Plan-Do-Check-Act

  
Login to rate this answer.
G.D.S.Prasad

Answered On : Mar 9th, 2009

A) Plan-Do-Check-Act

  
Login to rate this answer.
anuja_m

Answered On : May 26th, 2009

A) Plan, Do, Check and Act

  
Login to rate this answer.
kurtz182

Answered On : Dec 23rd, 2009

A) Plan-Do-Check-Act

Later, Dr. Deming changed this to Plan-Do-Study-Act (PDSA).

  
Login to rate this answer.

Give your answer:

If you think the above answer is not correct, Please select a reason and add your answer below.

Connect

twitter fb Linkedin GPlus RSS

Ads

Interview Question

 Ask Interview Question?

 

Career Counselling

 Have Career Question?

 Ask Chandra

 Ask Only Career questions.

Follow us:
 

Latest Questions

Ads

Interview & Career Tips

Get invaluable Interview and Career Tips delivered directly to your inbox. Get your news alert set up today, click "Subscribe".