Compile Source Records

I have 10 Million records in source and target 5 million records were populated then job was aborted again i go and compile and run the job when that time job will run from 5million 1 record to remain records how?

Showing Answers 1 - 3 of 3 Answers

Hari

  • Mar 9th, 2019
 

Use Upsert function in database connector stage. Or use lookup stage to perform lookup on the source and reference as your target data and load into your target stage