GeekInterview.com
  I am new, Sign me up!
 
GeekInterview.com  >  Interview Questions  >  Testing  >  Testing Scenarios
Go To First  |  Previous Question  |  Next Question 
 Testing Scenarios  |  Question 26 of 35    Print  
The top management has feeling that when there are any changes in the technology being used, development schedules etc, it was a waste of time to update the Test Plan. Instead, they were emphasizing that you should put your time into testing than working on the test plan. Your Project Manager asked for your opinion. You have argued that Test Plan is very important and you need to update your test plan from time to time. It’s not a waste of time and testing activities would be more effective when you have your plan clear. Use some metrics. How you would support your argument to have the test plan consistently updated all the time.

  
Total Answers and Comments: 4 Last Update: August 27, 2009     Asked by: sushkumar 
  
 Sponsored Links

 
 Best Rated Answer
Submitted by: surendra_kumar
 
Kalyani you have to understand the question  first. in fact instead of answering the question you have raised the same question once again in a different way.

The question itself demanding the answer with some metrics to defend it.

The answer is, wheather it is the change in the technology being used OR change in the development schedule it should be updated in the test plan. If not the whole concept of preparing the TEST PLAN itself is not usefull. 
 
 Test plan will also have all the time schedules mentioned in it w.r.t. the development schedules.which means it is highly dependent on the schedules commited by the Development team, so it becomes obvious to update the Test Plan also when there is a change in the Development shcedule to deliver the product in a timely manner.

As we all know the Test Plan is mainly made up of the elements like Testing Environment,Assumptions, Risk, Contigency Plan(mitigation plan),Effort estimation and Schedules,Hence its very obvious to update the Test Plan also for any changes in the Development schedules OR Technology, otherwise a Quality Product cant be delivered as per the schedule.
 
For any successfull Deliverables proper Planing is most important, and if that plan itself is not properly done (or not properly updated) may end up in a mess.

If someone feels it is not required to Update the TestPlan for any changes w.r.t. changes in Technology and Development Schedules, Then it is not required to go behind  the concept of Test Plan at all.

Above answer was rated as good by the following members:
vk1978
September 25, 2007 15:04:50   #1  
kalyani        

RE: The top management has feeling that when there are...
hi Test Plan is very important for testing phase.We have to define the metrics in test plan which describes about like all the requirements are covered or not through the test cases it means that we should define the test plan clearly.
 
Is this answer useful? Yes | NoAnswer is useful 0   Answer is not useful 2Overall Rating: -2    
June 16, 2008 23:18:53   #2  
surendra_kumar Member Since: November 2006   Contribution: 12    

RE: The top management has feeling that when there are any changes in the technology being used, development schedules etc, it was a waste of time to update the Test Plan. Instead, they were emphasizing that you should put your time into testing than work
Kalyani you have to understand the question first. in fact instead of answering the question you have raised the same question once again in a different way.

The question itself demanding the answer with some metrics to defend it.

The answer is wheather it is the change in the technology being used OR change in the development schedule it should be updated in the test plan. If not the whole concept of preparing the TEST PLAN itself is not usefull.

Test plan will also have all the time schedules mentioned in it w.r.t. the development schedules.which means it is highly dependent on the schedules commited by the Development team so it becomes obvious to update the Test Plan also when there is a change in the Development shcedule to deliver the product in a timely manner.

As we all know the Test Plan is mainly made up of the elements like Testing Environment Assumptions Risk Contigency Plan(mitigation plan) Effort estimation and Schedules Hence its very obvious to update the Test Plan also for any changes in the Development schedules OR Technology otherwise a Quality Product cant be delivered as per the schedule.

For any successfull Deliverables proper Planing is most important and if that plan itself is not properly done (or not properly updated) may end up in a mess.

If someone feels it is not required to Update the TestPlan for any changes w.r.t. changes in Technology and Development Schedules Then it is not required to go behind the concept of Test Plan at all.

 
Is this answer useful? Yes | NoAnswer is useful 1   Answer is not useful 0Overall Rating: +1    
March 19, 2009 08:34:55   #3  
srinivasulub1981 Member Since: December 2005   Contribution: 377    

RE: The top management has feeling that when there are any changes in the technology being used, development schedules etc, it was a waste of time to update the Test Plan. Instead, they were emphasizing that you should put your time into testing than work
Planning for any peace of work is very important if we have a good plan than we can complete the work in right time with quality even most of the projects and works getting late due to lack of plan.

Updating a plan is not a waste of time i think it's just take less than one day as for as my knowledge. I can tell to my PM below factors.

-> If we wanted to share our plan with client then how can we maintain??
-> If our plan was assigned for review by quality peopel then how can we maintain?
-> If our company goes to CMMI certifications and they wanted to see the plans then
how can we maitain?
-> Apart from all how can we keep track of the changes given client and all

 
Is this answer useful? Yes | No
August 27, 2009 11:33:09   #4  
jaya_bala Member Since: August 2009   Contribution: 1    

RE: The top management has feeling that when there are any changes in the technology being used, development schedules etc, it was a waste of time to update the Test Plan. Instead, they were emphasizing that you should put your time into testing than work
Effort variance schedule variance can be observed as and when the plan gets updated if the data is updated in the test plan on changes
 
Is this answer useful? Yes | No


 
Go To Top


 Sponsored Links

 
About Us -  Privacy Policy -  Terms and Conditions -  Contact -  Ask Question -  Propose Category -  Site Updates 

Copyright © 2005 - 2009 GeekInterview.com. All Rights Reserved

Page copy protected against web site content infringement by Copyscape