DMC Pile Foundation

How DMC Pile Foundation is done?

Questions by perfectclt

Showing Answers 1 - 3 of 3 Answers

In DMC Pile Foundation, the bentonite suspension is pumped into the bottom of the hole through the drill rods and it overflows at the top of the casing. The mud pump should have the capacity to maintain a velocity of 0.41 to 0.76metres per second to float the cuttings.

  Was this answer useful?  Yes


  • Jul 15th, 2011

means direct mud circulation.done by chisseling

  Was this answer useful?  Yes