Purpose

To prepare the traceability matrix, documenting the requirements identified in the project plan and during the first stage of the project.

The traceability matrix prepared in this task forms the baseline to be used in subsequent stages to confirm that all requirements have been met.


Document Baseline

Document the project requirements for both the application and the technical architecture.


Confirm Requirements

Ensure completeness by verifying that all of the requirements are included.

Showing Answers 1 - 3 of 3 Answers

Purpose

To prepare the traceability matrix, documenting the requirements identified in the project plan and during the first stage of the project.

The traceability matrix prepared in this task forms the baseline to be used in subsequent stages to confirm that all requirements have been met.


Document Baseline

Document the project requirements for both the application and the technical architecture.


Confirm Requirements

Ensure completeness by verifying that all of the requirements are included.