What are the 3 views and what is the purpose of each view?

Showing Answers 1 - 9 of 9 Answers

ram mohan

  • Dec 22nd, 2005
 

 

 

1 PLAN TEST

2 RUN TEST

3 TRACK DEFECTS

  Was this answer useful?  Yes

Usha

  • Dec 30th, 2005
 

U mean in QTP.

Tree view, Exper view, keyword View

  Was this answer useful?  Yes

Nag

  • Jan 5th, 2006
 

the three views in TD are

1. plan Test : which is used to prepare list of test cases by the test 

                   engineer by requirements wise 

2. Run Test : Which is used for executing the prepared test scripts

                   with respect to test cases

3. Track Defects: Test engineers are reporting  defects to developers

                       when a case is failed.

  Was this answer useful?  Yes

abhilasha

  • Jan 17th, 2006
 

Hi

The 3 views of requirment are:

 

1)Document View-tabulated view

2)Coverage View-establish a relationship between requirement and the test assosiated with them along with their execution status.Mostly the requirements are written in this view only.

3)Coverage analysis view-show a chart with requirementassociated with the test,and execution status of the test.

  Was this answer useful?  Yes

if its asking for the requiremnts module views then abhilasha is rite..

u can display document view, converage view and coverage analysis view of a requiremnt tree..

document view

by default the requirement module displays the requirements tree in document view ..it contains the following fields : name, cover status, reqID, author, reviewed, creation time

coverage view

you can also display the requirements tree in coverage view. this view enables you to add and modify tests coverage for your requirements more easily. test coverage tab contains the following fields :name,status execution time ....the tests are actually linked to the desired requirements.

coverage analysis view

i dont know the difference between coverage view n coverage analysis view?????

 

  Was this answer useful?  Yes

Sujatars

  • Jun 18th, 2007
 

3 views in TEst Director are

Plan Test:is used to designtest cases based on requirement.

Run Test:is ued to run/execute the test cases/test scripts based on manual or automated means on the application & analyze the result.

Track Defects:Reports defects detected in you application and track how it is progressing.

  Was this answer useful?  Yes