GeekInterview.com
  I am new, Sign me up!
 
GeekInterview.com  >  Interview Questions  >  Management  >  Project Manager
Go To First  |  Previous Question  |  Next Question 
 Project Manager  |  Question 30 of 35    Print  
Should a Project Manager be aggressive or assertive?
What is the difference between aggressiveness & assertiveness? Should a Project Manager be aggressive or assertive?


  
Total Answers and Comments: 4 Last Update: June 02, 2009     Asked by: uma101 
  
 Sponsored Links

 
 Best Rated Answer
Submitted by: b_sridhar76
 
Project Manager neither be aggressive nor assertive always. Project Manager should wear aggressiveness in some situations and assertiveness in majority of the situations.  e.g Your team member is asking for a leave which is a genuine but you have deadlines to complete the project due to that you cannot approve his leave.

In this situation, you should try to explain him milestone of the project and approves his leave if he stretches complete his scheduled work. ===> Assertiveness (WIN - WIN)

If you directly say "I cannot approve your leave" then this would motivate your team member.


Above answer was rated as good by the following members:
rkgopal nanduri
May 24, 2008 11:19:59   #1  
b_sridhar76 Member Since: May 2008   Contribution: 1    

RE: Should a Project Manager be aggressive or assertive?
Project Manager neither be aggressive nor assertive always. Project Manager should wear aggressiveness in some situations and assertiveness in majority of the situations. e.g Your team member is asking for a leave which is a genuine but you have deadlines to complete the project due to that you cannot approve his leave.

In this situation you should try to explain him milestone of the project and approves his leave if he stretches complete his scheduled work. > Assertiveness (WIN - WIN)

If you directly say "I cannot approve your leave" then this would motivate your team member.

 
Is this answer useful? Yes | NoAnswer is useful 1   Answer is not useful 0Overall Rating: +1    
June 07, 2008 13:17:08   #2  
BitBender Member Since: June 2008   Contribution: 2    

RE: Should a Project Manager be aggressive or assertive?
Assertive management is the correct posture for the project manager to assume when a matter of unscheduled leave impacts the project. But granting unscheduled leave places a greater burden on the project team as a whole. That fact must be assumed by the staff member asking for the leave and it should be stated that the workload added to the remaining staff will delay or jeopardize the success of the project.
Denying the leave will probably not motivate the team member to meet milestone requirements with the same level of quality. It will motivate others on the team to stretch their capability if the value of missing team member is deemed worthy of that effort. This would be a factor in team building. It would not be justification for schedule slippage.

 
Is this answer useful? Yes | No
September 30, 2008 23:32:47   #3  
rkgopal nanduri Member Since: September 2008   Contribution: 2    

RE: Should a Project Manager be aggressive or assertive?
The project manager should be aggressive and assetrive on the demand of the situation. He should be assertive on assesing the capabilities of the teams he is attached to and aggressive in time planning and it's implementations to attain the ultimate sucesses.
 
Is this answer useful? Yes | No
June 01, 2009 19:36:45   #4  
SomGollakota Member Since: June 2007   Contribution: 48    

RE: Should a Project Manager be aggressive or assertive?

Reviewing the answers below and getting a feel for the line of thinking therein I am compelled to say that a project manager must be neither aggressive nor assertive when it comes to resources and schedules. A project manager must be collaborative and realistic when it comes to teams and schedules. A project manager is not a “direct-line people manager” for the teams. A project manager has no real authority over the team members and does not “make up” a schedule.

Here is where the aggressiveness and assertiveness come into play.

A project manager must be aggressive in championing the cause of the project project team customer needs leadership directives and organizational processes and best practices both inward and outward (to the project teams).

A project manager must be assertive in times or chaos confusion and doubt to provide clear direction and leadership to the team.

A project manager is someone who has zero authority and 100 accountability over his/her team activities. Therefore the focus is on the softer skills – how to motivate teams how to collaborate with teams how to understand others’ perspectives how to ensure work-life balance to the team members how to communicate with them effectively how to listen how to make the team want to follow and how to get more commitments from the team (not because they “have” to commit more but because they “want” to commit more).


 
Is this answer useful? Yes | No


 
Go To Top


 Sponsored Links

 
About Us -  Privacy Policy -  Terms and Conditions -  Contact -  Ask Question -  Propose Category -  Site Updates 

Copyright © 2005 - 2009 GeekInterview.com. All Rights Reserved

Page copy protected against web site content infringement by Copyscape