On what basis can we say that a product is thoroughly tested and handed over to customer?

Showing Answers 1 - 18 of 18 Answers

Eno Demehin

  • Dec 13th, 2006
 

When the exit criteria has been made, this is subject to the recommendation made in the Master Testplan, if there is  no Business Requirement, product completion should be based on fitness of the product in terms of functionality.

  Was this answer useful?  Yes

Dharamakrishnan

  • Dec 16th, 2006
 

Hi

Number of text case written and which are executed against the specification

  Was this answer useful?  Yes

Akshay

  • Dec 18th, 2006
 

We can say product to thoroughly tested when the exit criterias that were decided in the begining are fulfilled.

  Was this answer useful?  Yes

Saritha

  • Dec 19th, 2006
 

When 100 % high severity bugs has been solved, all modules tested and when test duration completed

  Was this answer useful?  Yes

prasad

  • Dec 24th, 2006
 

hello,

Before the test execution we prepare a document called tracebility matrix. It deals with the two baseline documents..eg. usecases & test cases....we would be getting know all the test cases had been covered by this document. when all the test cases had been succusfully completed, there is nothing to do except exit criteria.

Prasad.Gandra

  Was this answer useful?  Yes

The answer to this question depends on the terms of contract.  In some cases, this condition is met by satisfying the exit criteria.  In other cases, an acceptance test is required by the customer. 