Submitted by: Sanju40148 In such a case its very important to compare the GR note and the PO order with the invoice. In other words three way match is very important.
If the supplier invoices more than $ 5000.00 in your example the invoice should not be paid. It is important to change the price in the PO in order to make the payment. Moreover its utmost imporant to check the arrival of the material in the plant.
To conclude you should not make the payment in case the price on the invoice is more than what was agreed and in order to pay the invoice is important to change the price in the PO.