What Is AIM In Oracle Financials? Where we can use this AIM?What is Role of AIM while Implementation Project?

Questions by sureshgupta_k

Showing Answers 1 - 9 of 9 Answers

Mahesh.A

  • Aug 6th, 2007
 

AIM is not a Module in ORA Apps like GL,AP,AR,etc,. It is an Implementation
Methodology which is recommended by Oracle for the successful Implementation of
Oracle E-Business Suite Projects.


In AIM (Application Implementation Methodology) there will be blank templates
available with the Software which will help us in proper Planning and Systematic
Implementation of the project by filling appropriate templates according to the
Modules we Implement. The concerned documents in general for,

Functional: BR100(Setup Doc), TE40(Testing Doc) and MD50(Module Design)

Technical: CV100 and MD70.


You People better catch this Link

www . oracleappsblog . com /index.php/weblog/comments/download-oracle-aim-applications-implementation-methodology-software-paper/

to get AIM Software, which contains all the required Doc's.Jus Peruse them and
ENJOY!

I Wish U All the Best. "Happy Friendship Day"

  Was this answer useful?  Yes

“A methodology is a set of guidelines or principles that can be tailored and applied to a specific situation.” In a project environment, these guidelines might be a list of things to do. A methodology could also be a specific approach, templates, forms, and even checklists used over the project life cycle. Therefore that was the driving factor for bringing AIM’s as methodology which was initially used by Oracle consulting , which is now most acceptable methodology for oracle application roll out.

The AIM Advantage product gives you all the tools you need to make your implementation successful by providing guidelines for:

* Business Process Architecture
* Business Requirements Definition
* Business Requirements Mapping
* Application and Technical Architecture
* Module Design and Build
* Data Conversion
* Documentation
* Business System Testing
* Adoption and Learning
* Performance Testing
* Production Migration


Processes

A process in AIM represents a related set of objectives, resource skill requirements, inputs, and deliverable outputs. A task can belong to only one process. Project team members are usually assigned to a process according to their specialization and background. A brief description of the AIM processes are given below:

1. Business Requirements Definition: Business Requirements Definition defines the business needs that must be met by the implementation project. You document business processes by identifying business events and describing the steps that respond to these events.

2. Business Requirements Mapping: Business Requirements Mapping compares the business requirements to standard application software functionality and identifies gaps that must be addressed to fully meet business needs. As gaps between requirements and functionality emerge, they are resolved by documenting workarounds, alternative solutions, application extensions, or by changing the underlying business process.

3. Application and Technical Architecture: During the Application and Technical Architecture you design an information systems architecture that reflects your business vision. Using the business and information systems requirements, this process facilitates development of a plan for deploying and configuring the hardware required for a successful implementation.

4. Module Design and Build: Module Design and Build produces custom software solutions to gaps in functionality identified during Business Requirements Mapping. Custom software solutions include program modules that must be designed, built, and tested before they can be incorporated into the system.

5. Data Conversion : Data Conversion defines the tasks and deliverables required to convert legacy data to the Oracle Applications tables. The first step of this process explicitly defines the business objects that are required for conversion and the legacy source systems that store these objects. The converted data may be needed for system testing, training, and acceptance testing as well as for production.

6. Documentation :Documentation begins with materials created early in the project. Using detailed documents from the project, the writing staff develops user and technical material that are tailored to the implementation.

7. Business System Testing: Business System Testing focuses on linking test requirements back to business requirements and securing project resources needed for testing. It supports utilizing common test information including data profiles to promote testing co-ordination and to minimize duplication of test preparation and execution effort.

8. Performance Testing:Performance Testing enables you to define, build, and execute a performance test. Use the results to make decisions on whether the performance is acceptable for the business and to help propose tactical or strategic changes to address the performance quality shortfall. Performance Testing is closely related to Application and Technical Architecture; they are interdependent.

9. User Training:Training prepares both users and administrators to assume on the tasks of running the new application system. It includes development of materials and methods as well as administration. Instructors and courseware developers orient their material toward roles and jobs, and not toward application modules.

10.Production Migration : Production Migration moves the company, system, and people to the new enterprise system. Following production cutover, it monitors and refines the production system and plans for the future. The Production Migration process encompasses transition to production readiness, production cutover, and post-production support

Phases

An AIM project is conducted in phases that provide quality and control checkpoints to co-ordinate project activities that have a common goal. During a project phase, your project team will be executing tasks from several processes. A brief description of the AIM processes are given below:

1. Definition: This consist of review the organization’s business objectives, evaluate the feasibility of meeting those objectives under time, resource, and budget constraints. Moreover this can be best consider as SOW(statement of work) preparation phase.

2. Operations Analysis:During Operations Analysis, the project team develops Business Requirements Scenarios based on deliverables from Definition that are used to assess the level of fit between the business requirements and standard application functionality. Gaps are identified and corresponding solutions developed. The analysis results in a proposal for conducting business operations under the envisioned application technical architecture. Solutions for gaps evolve into detailed designs during Solution Design.

3. Solution Design:The purpose of Solution Design is to develop the detailed designs for the optimal solutions to meet the future business requirements. During this phase, project team members create detailed narratives of process solutions developed during Operations Analysis. Supporting business requirements may require building application extensions to standard features; several alternative solutions may have been defined during Operations Analysis. The project team carefully scrutinizes these solutions and chooses the most cost effective alternatives.

4. Build:The coding and testing of all customizations and other custom software including enhancements, data conversions, and interfaces is done during Build. Policy and procedure changes relating to business process modifications are developed. Business system testing is performed to validate that the developed solutions meet business requirements. If customizations, extensions, or conversions are not required, Build is still important because it includes the business system test, which is commonly conducted as a formal conference room pilot. The business system test validates the solutions and is performed in an environment that closely resembles production.

5. Transition: During Transition, the project team deploys the finished solution into the organization. All the elements of the implementation must come together to transition successfully to actual production. The project team trains the end users while the technical team configures the production environment and converts data. Transition ends with the cutover to production, when end users start performing their job duties using the new system.

6.Production: Production begins immediately with the production cutover. It marks the last phase of the implementation, and the beginning of the system support cycle. Included in this final phase is a series of refinements and performance measurement steps. The inhoues MIS/IT Department personnel work quickly to stabilize the system and begin regular maintenance. They will provide the ongoing support to the organization for the remaining life of the system. During Production, you compare actual results to project objectives.