Please give me explaination of 'V' model steps,e.g.What is releation between requirment anaylsis & acceptance testing.

Showing Answers 1 - 3 of 3 Answers

Ganesh

  • Jun 20th, 2006
 

Hi,

V Model consits of Process at one end and Testing at other end.

Process consits of URS->SRS->HLD->LLD->Code

Testing consits of UT->IT->ST->UAT

Where each step in Process is equiated with Testing ...

  Was this answer useful?  Yes

Bharath

  • Jun 28th, 2006
 

Hi

After copmletion of every develpment phase the coresponding testing should be statrted

During develpoment vmodel follows water fall model

After completion of testing and during maintainance managment team find out's the efficiency of testing team

T.E=A/(A+B).

and the one and only drawback is maintance of testing team is very high so it is not suitable for small/middle scale companies