Do leave hours considered in effort variance calculation?

I have a generic query related to Effort Variance.
The formula says ((Planned Effort - Actual Effort) / Planned Effort)*100.
So here if a resource had taken leave for 2 working days, do we consider that leave duration in Actual Effort or the calculation should exclude the leave hours?

 