Calculate Number of Oil Pipes Required

Pipes are laid by an oil company. If the company has to laid down 3 km of pipe and each pipe is 25 metres long, calculate and print the number of pipes needed to cover the distance.

Showing Answers 1 - 3 of 3 Answers

Guddu

  • May 19th, 2016
 

Total Distance = 3 x 1000 m = 3000m
Number of pipe required = 3000/25 = 120

  Was this answer useful?  Yes