What is the difference between FRS, PRD, TRD, SRS, MRD, BRD?

Showing Answers 1 - 5 of 5 Answers


  • Jul 27th, 2006

FRS means Functional Requirement Specifications,SRS means System Requiremen Specification,BRD means Business Requirement Documentation i havn't comacross the other 3...i think all these are related to the requirements given by the clients for the development of the application or product..etc..its the different terminology but meaning is same with a little difference....i think this information is adequate...

  Was this answer useful?  Yes


  • Aug 8th, 2006

SRS: System requirement specification used mostly in product companies to define the product requirements from the customer.

MRD: Mission requirements document is used in bigger govt projects to define requirements of a mission[project] . EG:Defence, Space/satellite programmes

TRD: Technical requirement document is used once again in airforce,Space/satellite programmes to define technical requirements

Remember there is a subtle difference in each of the terminologies defined above and their usage. All are not same

  Was this answer useful?  Yes


  • Sep 11th, 2006

FRS->Functional requirement specification

PRD->Public relation departemennt

TRD->Testing resource development

SRS->System requirement specification

MRD->Marketing Resource developnment

BRD->Bussiness requirement documentation

 sudhakar kolla

If you are having any doubt can ask me.

My Email:Kollasudhakar2005@yahoo.co.in

My number :09819859346


  Was this answer useful?  Yes


  • Mar 4th, 2010

Above answer is about half right.

FRS->Functional requirement specification
***PRD->Product Requirements Document***
***TRD->Testing Requirements Document***
SRS->System requirement specification
***MRD->Marketing Requirements Document***
BRD->Business requirement documentation

  Was this answer useful?  Yes


  • Mar 13th, 2010

FRS - Functional requirement specification
PRD - Public relation departemennt
TRD - Testing resource development
SRS - System requirement specification
MRD - Marketing Resource developnment
BRD - Bussiness requirement documentation

  Was this answer useful?  Yes

Give your answer:

If you think the above answer is not correct, Please select a reason and add your answer below.

Answer Question

Click here to Login / Register your free account

Send   Reset


Related Answered Questions


Related Open Questions