A works thrice as much as B. If A takes 60 days less than B to do a work then find the number of days it would take to  complete the work if both work together?

22½ days

Showing Answers 1 - 7 of 7 Answers

rekha

  • Oct 13th, 2006
 

As the efficiency of doing work is 1:3 the days required are less for A.so propotion will be x : 3x = y-60 : yafter solving xy=90 sp y = 90/xfor A , x =1 so y = 90for B, x= 3 so y = 30par day work 1/90+1/30= 4/90so to complete the whole work time required 90/4 = 22 and 1/2

  Was this answer useful?  Yes

Answer 22.5 day

Let B complete the 1 part of job =1/x day
according 2 question.
3/x=1/x-60
 
Solving
x=90 
B complete job=90 day
A complete the job=30 day
 
When both doing then
1/90+1/30
4/90
Complete the job
90/4= 22.5 day Answer.