How to run 10 jobs at the same time in DataStage 8.0.1?

Questions by praveen.bollu

Showing Answers 1 - 2 of 2 Answers

j.padma89

  • Jul 14th, 2011
 

To run 10 or any number of jobs one after the other or in any sequence, One can use "job sequences".
In each sequence one can assign a job, so after the 10 sequences , you can run a sequence job.
Using sequential jobs developer can even decide what should a job do if it is aborted.

  Was this answer useful?  Yes