A certain number of men can finish a piece of work in 10 days. If however there were 10 men less it will take 10 days more for the work to be finished. How many men were there originally?(a) 110 men(b) 130 men(c) 100 men(d) none of these

This question is related to Accenture Interview

Showing Answers 1 - 75 of 114 Answers

srini

  • Feb 17th, 2006
 

none of these. actuallythereare 10 mens, if 10 mens do not work then it will take 10 more days to finish

jayanthi

  • Apr 19th, 2006
 

ans : none of these

x-10:x = 10:20

20x-200 =10x

10x = 200

x=20

sandeep meela

  • Apr 23rd, 2006
 

i suppose answer is a . wat would be the answer whether i m correct r not?

  Was this answer useful?  Yes

infor

  • May 1st, 2006
 

Since the number of days for each men to finish the same work will remain same even if we increase the men or not. This goves us two equations which are equal. Say x men are there initially. x mean finish in 10 days so each men can finish the same work in 10x days. Now lets say we reduce men by 10, then we have x-10 men and numner of days is 20. so

10x=(x-10)20 which is 10x=200 so x= 20 men in the begining.

  Was this answer useful?  Yes

k.avinash

  • May 25th, 2006
 

 its none of these , the answer is 20 

  Was this answer useful?  Yes

prasanna

  • Jun 26th, 2006
 

let x be original no of menx --------> 10 daysx-10------>10+10 daysby inverse proportionalityx*10 = (x-10)*20x = 20None of these

  Was this answer useful?  Yes

Basheer

  • Aug 6th, 2006
 

Ans) D

  (x-10) : x  =  20 : 10

   20x-200  =  10x

   20x-10x  =  200

    x  =  200/10

    x  =  20

  Was this answer useful?  Yes

rahul

  • Oct 6th, 2006
 

none of these

  Was this answer useful?  Yes

yogeshgurav007

  • Feb 7th, 2007
 

Suppose X men does same work in 10 days
X-10 men does same work in 20 days
cross20X = 10X - 10010X = -100X = -10
means nobody there on work

Ans is D> none of these

  Was this answer useful?  Yes

let x men can finish it in 10 days    ( 1 man can finish it in 10x days)

then x-10 can finish it in 20 days   (1 man can finish it in 20(x-10) days)

here no of men is decreasing so no of days will be more to finish work( from above statements it is true )

since it  is indirectionally proportional 

10 * x = 20(x-10);

10x = 200;

x=20 ;ans :20

 

 

  Was this answer useful?  Yes

anand3186

  • Jul 16th, 2009
 

Let no of men  = x.
x men can do a piece of work in 10 days.
so, 1 man can do it in 10*x days.
Now (x-10) men do the work in 20 days.
so, 1 man ... in 20*(x-10).
so, 20(x-10) = 10x.
so, x = 20.
Ans is option (d).

  Was this answer useful?  Yes

Kaviya

  • Apr 25th, 2014
 

110

  Was this answer useful?  Yes

kiransai

  • Sep 12th, 2014
 

Here decrease of men results to increasing in work ie ab=K==>a=K/b ie one increases and the other decreases
So for this type of qtns take comparison of 2 eqtns as
10x=(10-x)20==>x=20 men required

  Was this answer useful?  Yes

VENKAT KRISHNAN V R

  • Nov 6th, 2014
 

10x = (10+10)(x-10) giving x = 20

  Was this answer useful?  Yes

vghj

  • Feb 27th, 2015
 

1

  Was this answer useful?  Yes

veru

  • Mar 5th, 2015
 

none of these

  Was this answer useful?  Yes

sudha

  • Jul 19th, 2015
 

How x came as 100? x is 10 only

  Was this answer useful?  Yes

althaf

  • Aug 17th, 2015
 

(d) none of these

  Was this answer useful?  Yes

sethulakshmy

  • Sep 14th, 2015
 

(d).None

  Was this answer useful?  Yes

ennar4u

  • Nov 19th, 2015
 

Using formula M1*D1= M2*D2
=> x*50 = (x+6)*40
=>50x - 40x = 240
=>x = 240/10
=>x = 24 men
Originally 24 men worked

  Was this answer useful?  Yes

kaushal

  • Jun 9th, 2016
 

(a) 110 men

  Was this answer useful?  Yes

Hammed Abid

  • Jun 9th, 2016
 

x*10=(x-10)*20
10x=20x-200
200=10x
x=20

  Was this answer useful?  Yes

nivya

  • Jul 14th, 2016
 

(a) 110 men

  Was this answer useful?  Yes

Anu

  • Sep 24th, 2016
 

how by 20x=10x-100
we will get x=100

  Was this answer useful?  Yes

arif khan

  • Oct 21st, 2016
 

Suppose x men take 10 days => 1 man will take 10 * x days
(for clarification think reverse process 1 man in 10 * x days so x men will do in (10*x)/x=>10)

Now x-10 men do in 20 days => (10x/(x-10))=20 => x=20 hence the answer :-)

  Was this answer useful?  Yes

S. Manoj kumar

  • Nov 17th, 2016
 

How can You say its 110?

  Was this answer useful?  Yes

Debarati

  • Nov 18th, 2016
 

x= Initial no. of men
y= Total work

y/x=10
y/(x-10)=20
10x=20x-200
10x=200 x=10 men :)

  Was this answer useful?  Yes

techgigg

  • Jan 30th, 2017
 

Ans : x * 10= (x-10) * 20
x=20

  Was this answer useful?  Yes

Vidhi

  • Feb 6th, 2017
 

Total Work=Total No. of time required * Total No. of man to perform work so, here....total day for x man is 10
total day for x-10 man is 10+10=20
10*x=(x-10)*20
10x=20x-200
therefore, x=100

  Was this answer useful?  Yes

Arnab Khan

  • Jun 28th, 2017
 

x/10=(x-10)/20
=>x=100
initially there was x+10=110 man

  Was this answer useful?  Yes

Saurabh

  • Aug 22nd, 2017
 

10x=20x-200 gives x=10 not 100.

  Was this answer useful?  Yes

Pallavi Valunj

  • Aug 29th, 2017
 

(d) none of these

  Was this answer useful?  Yes

pratap

  • Aug 31st, 2017
 

x=10
x-10=10+10
x=30
Ans: 30 men

  Was this answer useful?  Yes

pooja sharma

  • Sep 14th, 2017
 

d) none of the above
Explanation:
let x=10;
x-10 =20;
(x-10)*20=10x;
x=20;

  Was this answer useful?  Yes

Lakshmi priya

  • Sep 22nd, 2017
 

let x be the number of men
x can do their work in 10 days
x=10
if x decreases by 10 days increases by 10
x-10=20
x=30
ans:none of the above

  Was this answer useful?  Yes

Amit Mangal

  • Nov 28th, 2017
 

x*10=(x-10)*20
10x = 20x - 200
-10x = -200
x = 20

  Was this answer useful?  Yes

Tanuj Kapoor

  • Jan 29th, 2018
 

Check your calculation again
20x=10x-100 will give x=10 not 100
so x+10=20
hence answer is none of these

  Was this answer useful?  Yes

angy

  • Feb 9th, 2018
 

y/10-10/1=10,so when all cancels out,we have y-10=10,when 10 goes in the place of y and vice-versa,he y=0,so the answer is none of these

  Was this answer useful?  Yes

Ankit

  • Aug 26th, 2018
 

130

  Was this answer useful?  Yes

ganesh

  • Oct 4th, 2018
 

130 men

  Was this answer useful?  Yes

jyotika

  • Mar 6th, 2019
 

D (real answer is 20)

  Was this answer useful?  Yes

Give your answer:

If you think the above answer is not correct, Please select a reason and add your answer below.

 

Related Answered Questions

 

Related Open Questions