Peoplesoft upgrade

You are in middle of an upgrade System Integration testing, When there is a need to apply the latest Maintenance Pack for the higher version, What steps or options will you follow and where will you apply the MP?
1) Apply MP on Higher Version Demo used for Upgrade and evaluate impact
2) Apply MP on a copy of Higher Version Demo used for upgrade and evaluate Impact.
3) After fixing objects in MP for upgrade, move it to the Initial Move Source so that it can come through each test move.
4) Apply MP project after completing steps for Upgrade. So that upgrade steps are not impacted
o 1 and 3
o 2 and 4
o 1 and 4
o 1,3,4

Questions by dorsalad

Showing Answers 1 - 6 of 6 Answers

henny

  • Nov 23rd, 2016
 

1 and 3

  Was this answer useful?  Yes

Reena

  • Jan 18th, 2017
 

2 and 4
Because applying maintenance on the participating environments can break the Data Conversion. So its best to test it on the copy of one of the upgraded environments to test the impact and then apply it on the target after upgrade is completed.

  Was this answer useful?  Yes