Explain about Metrics and types of metrics like schedule variance , effort variance?

Questions by sree880   answers by sree880

Showing Answers 1 - 15 of 15 Answers

Naseem

  • Dec 6th, 2005
 

Schedule Variance =

((Actual Duration - Planned Duration)/Planned Duration)*100

Effort Variance =

((Actual Effort - Planned Effort)/planned effort) *100

                              

  Was this answer useful?  Yes

lokeshwari

  • Mar 2nd, 2006
 

Explain about Metrics and types of metrics like schedule variance , effort variance?

  Was this answer useful?  Yes

Parameshwaran

  • Oct 27th, 2006
 

HI Naseem,

         Here you have given the formula for Effort variance is (Actual - Planned Effort)/ Planned Effort or (Actual - Estimated) Estimated effort) Can you pls tel which is right? I would like to what is the difference between planned and the estimated effort. Is it right insted of plan if we use stimated.

Kindly explian the reason - Email id is rvs.svr@gmail.com

  Was this answer useful?  Yes

TechyStuff

  • Mar 7th, 2009
 

Planned Effort is the actual estimate you received from the Client. If you do your own estimate based on the planned effort you get from the client then that will be a different scenario.


Regards,
Techystuff

  Was this answer useful?  Yes

Variance is the difference between the plan and actual. It could be anything
(budget, schedule, effort, resources, scope, quality, performance - any
measurable item in a project that we can plan for). It can be a zero, positive
or a negative variance. While positive variance means bad planning, a zero
variance or negative variance could mean good planning. However, too much of
negative variance (over 10%) could mean bad planning as well.


Consider the following.
Planned budget - $10 Million
Actual Cost at completion - $11 Million
Budget Variance – Actual – Planned = $11 Million - $10 Million = $1 Million
(Project is Over by $1 million – bad planning, bad budget management)


Planned budget - $10 Million
Actual Cost at completion - $9.5 Million
Budget Variance – Actual – Planned = $9.5 Million - $10 Million = -$0.5 Million
(Project is under budget by $500 K, good planning and effective project
management)


Planned budget - $10 Million
Actual Cost at completion - $5 Million
Budget Variance – Actual – Planned = $5 Million - $10 Million = -$5 Million
(Project is grossly under budget, by 50%. Bad planning and bad management – the
project planner grossly overestimated the project and locked up $5 Million of
the company’s money that could have been better spent elsewhere).

av45738

  • Nov 20th, 2009
 

Effort Variance= (Actual effort-estimated effort)/Estimated effort*100

Schedule Variance=(Actual elapsed time- estimated elapsed time)/estimated elapsed time*100

  Was this answer useful?  Yes

parameshwar.V

  • Dec 17th, 2013
 

Effort Variance should be (Actual Effort - planned Effort)/ Planned Effort.

EV should calculate w.r.t Person Days.

Schedule variance should be (Actual End Date - Planned End Date)/Planned End Date.

SV should calculate w.r.t Person Hours.

  Was this answer useful?  Yes

Give your answer:

If you think the above answer is not correct, Please select a reason and add your answer below.

 

Related Answered Questions

 

Related Open Questions