Recurring Activities in Waterfall Method

Which of the following are the recurring activities in modified waterfall method
a)
Review
b) Final Inspection
c) Requirement traceability
d) Warranty and support

i) A
ii) A,C,D
iii) D
iv) A,B,C

Questions by sasghosh

Showing Answers 1 - 7 of 7 Answers

ds1164

  • May 31st, 2009
 

iv) Review, Final Inspection and Requirement Traceability may occur more than once in waterfall method.