What is entry and exit criteria of a test plan?

Questions by richas

Showing Answers 1 - 10 of 10 Answers

Hari Kishan

  • Mar 16th, 2006
 

Entry Criteria :  Project Kickoff Meeting and DSRS should be approved

Exit Criteria   :  Reviewed, Approved and Base-Lined QATP

  Was this answer useful?  Yes

Joshna

  • Mar 17th, 2006
 

Requirements must be met to move from one phase to another of the SDLC..

A phase cannot be left until exit criteria are met & a phase cannot be entered until entrance criteria is met..

For example:Exit Criteria: Beta stage might begin only when the acceptance test with no bugs found has been completed. i.e the exit criteria of acceptance test has been met.. 

similarly for entrance criteria: Formal Spec may be published when the spec review is over & authorised..

  Was this answer useful?  Yes

madhan

  • Mar 31st, 2006
 

The Entry and Exit Points of the Test Plan are

  1. Requriments ( To nalyze the Product)
  2. Function and Design Specifications( HLD,LLD) ( To understand the Features)
  3. Project Plan(Scheduling)
  4. Previous Records (Compare the Privous records)

  Was this answer useful?  Yes

sundar

  • May 20th, 2006
 

ENTRY CRITERIA: SRS and FSEXIT CRITERIA : Once the test plan is got approved by client

  Was this answer useful?  Yes

epemolu

  • May 24th, 2006
 

hello guys, please what do this terms mean, DSRS,QATP,SDLC,SRS. Thanx

  Was this answer useful?  Yes

hema_3078

  • May 27th, 2006
 

Entry Criteria: What inputs are required to start a perticular work or phase. Exit Criteria: What deliverables are expected from the completion of work or phase.

  Was this answer useful?  Yes

Radhika Appasani

  • Jun 1st, 2006
 

hey  DSRS,QATP,SDLC,SRS

DSRS-------Detailed System Requirements Specification (working with team to design and document the specifics of operation and technology)

QATP----------Quality Assurance Testing Plan

SDLC-----software development life cycle

SRS------software requirement specification

  Was this answer useful?  Yes

Susanta Behera

  • Oct 2nd, 2006
 

Entry Criteria:--Functional and Non Functioal List to be Tested

Exit Criteria:-- Required Procedure