    what is end to end testing and where/at what stage we can apply the end to end testing?

    Last edited by jainbrijesh; 09-20-2007 at 08:12 AM.

  2. #2
    Contributing Member
    Join Date
    Feb 2006
    Answers
    85
    End-to-end testing is the process of testing transactions or business level products as they pass right through the computer systems. Thus this generally ensures that all aspects of the business are supported by the systems under test.

    This ensures that the overall process flows as expected, that is that system components integrate together correctly and that the right information is passed between them.

    The process may fail and there could be omissions in the process. Dependencies may not have been identified and incorrect information could be passed between system components and systems. The software may work, but the overall process does not (for example, people order goods, but they are never delivered).

    so this doesn't mean that the individual modules are not working properly but there communication is not proper or somewhere some piece is not working or missing from the whole system.

    When can we start?
    thats a tricky Question as it can be at any stage depend on the sixe of the product but the basic criteria is all the individual modules are working fine...

    Thanks,
    Kunal.

    End-to-end testing is the process of testing transactions or business level products as they pass right through the Computer systems. Thus this generally ensures that all aspects of the business are supported by the systems under test.

    This ensures that the overall process flows as expected, that is that system components integrate together correctly and that the right information is passed between them.

    The process may fail and there could be omissions in the process. Dependencies may not have been identified and incorrect information could be passed between system components and systems. The software may work, but the overall process does not (for example, people order goods, but they are never delivered).

    so this doesn't mean that the individual modules are not working properly but there communication is not proper or somewhere some piece is not working or missing from the whole system.

    When can we start?
    thats a tricky Question as it can be at any stage depend on the sixe of the product but the basic criteria is all the individual modules are working fine...

    Thanks,
    Kunal.

    Last edited by jainbrijesh; 09-20-2007 at 08:13 AM.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
About us
Applying for a job can be a stressful and frustrating experience, especially for someone who has never done it before. Considering that you are competing for the position with a at least a dozen other applicants, it is imperative that you thoroughly prepare for the job interview, in order to stand a good chance of getting hired. That's where GeekInterview can help.
Interact