-
Contributing Member
how will we prepare summary report
summary report for a testing project
-
Expert Member
Re: how will we prepare summary report
hi friend...
According to IEEE-829, the summary report should include:
1.Summary 2.Variances 3.Comprehensiveness assessment 4. Summary of results 5.Evaluation 6.Summary of activities
The summary report should include what software was tested including version number and a description of the software and hardware environment. It should reference the test plan, test logs and test incident reports.
It should describe in the variance section how certain tests described in the test plan were not followed exactly and what additional tests were performed beyond the test plan.
The comprehensiveness assessment should include an evaluation of what features or feature combinations of the software were not sufficiently tested and are expected to contain a subjective assessment.
The summary of results and evaluation should include a description of all incidents and whether they were resolved, and provide an overall evaluation of the testing and an estimate of the general reliability of the software.
The summary of activities describes the effort level and calendar time needed for performing different aspects of the testing.
Thanks
Deepasree
Posting Permissions
- You may not post new threads
- You may not post replies
- You may not post attachments
- You may not edit your posts
-
Forum Rules