  1. Re: Inactivating Users in Quality Center 9.0

    Hi,

    Reply given by quality_quantity is not related to my question i guess as there is no point of matching existed.

    But for my question i got a solution like taking the list of users existed...
  2. Answers
    11
    Views
    20,360

    Re: QC Release Module

    The Release Module

    You define releases and cycles in Quality Center using the Releases module, which is opened by clicking the Releases button on the sidebar.

    The Releases module contains the...
  3. Answers
    11
    Views
    20,360

    Re: QC Release Module

    Assigning Defects to Releases

    1)If an application flaw is detected while running a test set, the QA engineer can submit a defect. Quality Center automatically creates a link between the test run,...
  4. Answers
    11
    Views
    20,360

    Re: QC Release Module

    Assigning and Running Test Sets in Release Module

    1)After the QA manager assigns requirements, the QA team leader assigns each test set folder in the Test Lab module to a cycle. A test set is a...
  5. Answers
    11
    Views
    20,360

    Re: QC Release Module

    Assigning Requirements to Releases

    1)After defining the releases tree, the QA manager defines and reviews the requirements in the Requirements module and assigns them to releases and cycles....
  6. Answers
    11
    Views
    20,360

    Re: QC Release Module

    Defining Releases and Cycles:

    1)The foundation of the Releases module is the releases tree. This tree enables the modeling of upcoming releases within a hierarchical tree structure.

    2)A...
  7. Answers
    11
    Views
    20,360

    Re: QC Release Module

    The release management work flow you begin the application testing process by defining a releases tree in the releases module. The release management workflow consists of the following stages. Define...
  8. Answers
    6
    Views
    4,081

    Re: Tuser

    Oh tht's gr8.

    All the best...

    Can contact me at any time if needed.

    Regards
    Deepika.P
  9. Answers
    6
    Views
    4,081

    Re: Tuser

    Hi,

    We can only Add or Delete a user and we can only Rename a user group but Renaming a user is not existed as far as i know.

    Please tell me if you can do that.

    Thanks
    Deepika.P
  10. Answers
    6
    Views
    4,081

    Re: Tuser

    Hi,

    you want the QCUser name to be displayed as user full name in Test Plan,Test Lab and Defects modules??
  11. Re: Shows subject and test name, but all steps are missing

    Hi,
    I guess u hadn't merged the cells Subject.....for example if we have TestName 1 and if it has steps like a,b,c then we need to merge the three rows of Subject and TestName.Then you can give...
  12. Re: Filling "Date Creation" field with the current day

    Hi, you can write the vb code in setup work flow.this can be found in customization.in the setup work flow select the defects module,then defects field can change...in this wirte the following...
  13. Adding Attachment in the TestLab Module

    Hi,
    In the TestLab module we can add an attachment manually to a TestSet.But is there any possibilty that when we run tests automatically then that particular sheet related to those tests...
  14. Answers
    1
    Views
    5,951

    Fields in Test lab execution grid

    Hi,
    In the execution grid we see different fields....we have a button called "Select Columns" in the toolbar.In that Select Columns we can make fields we need as visibile by selecting from...
  15. Upload Defects in to Quality Center

    Hi,
    Iam trying to upload defects from excel sheet in to QC.I uploaded 245 defects when i tried to upload remaining iam getting "Over Flow" error when i select more than 10 defects at a time.If...
  16. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    If you have any doubts still in creating projects or assigning users can ping me back.I can help you always as iam working as QC Admin.

    Thanks
    Deepika.P
  17. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    4.select users from the users list or projects list, and click the add selected users to the project button . The selected users are displayed in the project users list. 5.to remove a user from a...
  18. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    3.click the add button,and choose one of the following options: a)add from the users list: the users list is displayed to the right of the project users tab. Select the users that you want to assign...
  19. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    You can click the User Name or Full Name column to change the sort order of user names or full names in the Project Users list from ascending to descending. You can also click the Project...
  20. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    To assign users to a project:

    1.In Site Administration, click the Site Projects tab.

    2.In the Projects list, select a project. In the right pane, select the Project Users tab.
    The users for...
  21. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    Note:

    1.As a Quality Center project administrator, you can assign and remove users from projects, and change user privileges from the Project Customization window.

    2.You can assign projects to...
  22. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    When a user is no longer working on a project, you should remove the user from the project to ensure project security. Note that removing a user from a project does not delete the user from the...
  23. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    Assigning Users to Projects

    As a site administrator, you can control access to Quality Center projects by defining the users that can log on to the project. You can assign users to projects from...
  24. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    12.click next. Verify the project details. To change any of the details, click back.

    13.you can select activate project to instruct quality center to activate the new project.

    14.you can...
  25. Answers
    17
    Views
    14,948

    Re: Creating Projests and users

    The selected users are displayed in the selected project administrators list.

    Note: you can also assign project administrators after you have created the project. -to remove a user from the...
Results 1 to 25 of 59
Page 1 of 3 1 2 3
About us
Applying for a job can be a stressful and frustrating experience, especially for someone who has never done it before. Considering that you are competing for the position with a at least a dozen other applicants, it is imperative that you thoroughly prepare for the job interview, in order to stand a good chance of getting hired. That's where GeekInterview can help.
Interact