  • Datastage scenario Question

    A Sequences is calling activity 1, activity 2 and activity 3.while running, activity 1 and 2 got finished but 3 got aborted. How can I design a sequence such that the sequence has to run from activity 2 when I restart the sequences?

    Ritwik

    • Apr 21st, 2014

    You have to check the " Do not checkpoint run " checkbox for activity 2. If you set the checkbox for a job that job will be run if any of the job later in the sequence fails and the sequence is restarted.