  • Transformer OC Test

    Why OC test is conducted on low voltage side?

    A.santosh

    • Jan 27th, 2012

    If want to conduct OC test on HV side we need more turns of auto-transformer, as an engineers we should have to decrease the cost required for the test, so normally OC test is conducted on LV side since we need less turns of auto-transformer

    sinhasunilk

    • Jul 12th, 2010

    Voltage injection in LV side is convenient, The cable attached to LV side also need insulation suitable to LV voltage rating. If LV ia in the range of 440V and HV is of the range of 11KV, we may inject voltage in steps also through variac of 440V , Which is not possible if inject voltage in HV side.