    Hi,

    I would like to know whether the schedules for testing needs to be included in test plan or not? And also what type of risks can be identified in test plan other than schedule variance?

    Regards,
    Neel.


  2. #2
    Expert Member
    Join Date
    Oct 2007
    Answers
    375

    Re: Schedules in test plan

    Hi Neel,

    a test plan can definitely encompass test scheduling. You can include the start date, dates for various milestones to be achieved and the estimated end date of testing.

    You can also specify the entry, exit, suspension and resumption criteria for testing.

    As regards risk, we would have a seperate section detailing out risks involved and their respective mitigation plans. A few risks that are generally covered are -

    • application availability for the entire period of testing
    .
    • Availability of a dedicated testing environment.


    Both the above questions pertain to schedule variance as these risks can vary the planned schedule.

    • QA schedule dependency on build delivery from dev team and their delivering a testable product.

    • Adhoc change requests could cause variance in testing schedule.

    • Undocumented change requests leading to inadequate test coverage.


    I hope this helps a bit...

    Cheers......

    Last edited by bizzzzzare; 06-26-2008 at 09:47 AM. Reason: Better Formating

  3. #3
    Expert Member
    Join Date
    Jan 2007
    Answers
    141

    Re: Schedules in test plan

    Hi Neel,

    Yes Schedule should be included in Test plan.This schedule helps the test plan to identify the task needs to be undertaken at each level of testing.

    Here is the link which has sample schedule for the test plan.

    http://members.tripod.com/~bazman/frame.html

    “Risk are the future uncertain events with a probability of
    occurrence and a potential for loss”. Risk identification
    and management are the main concerns in every software
    project. Effective analysis of software risks will help to
    effective planning and assignments of work.

    Categories of risks:

    Schedule Risk:
    Project schedule get slip when project tasks and schedule
    release risks are not addressed properly. Schedule risks
    mainly affect on project and finally on company economy and
    may lead to project failure. Schedules often slip due to
    following reasons:

    1) Wrong time estimation
    2) Resources are not tracked properly. All resources like
    staff, systems, skills of individuals etc.
    3) Failure to identify complex functionalities and time
    required to develop those functionalities.
    4) Unexpected project scope expansions.

    Budget Risk:

    1) Wrong budget estimation.
    2) Cost overruns
    3) Project scope expansion

    Operational Risks:

    Risks of loss due to improper process implementation, failed
    system or some external events risks. Causes of Operational
    risks:

    1) Failure to address priority conflicts
    2) Failure to resolve the responsibilities
    3) Insufficient resources
    4) No proper subject training
    5) No resource planning
    6) No communication in team.

    Technical risks:
    Technical risks generally leads to failure of functionality
    and performance. Causes of technical risks are:

    1) Continuous changing requirements
    2) No advanced technology available or the existing
    technology is in initial stages.
    3) Product is complex to implement.
    4) Difficult project modules integration.

    Programmatic Risks:
    These are the external risks beyond the operational limits.
    These are all uncertain risks are outside the control of the
    program. These external events can be:

    1) Running out of fund.
    2) Market development
    3) Changing customer product strategy and priority
    4) Government rule changes.


    Hope these gives you brief idea on Risk concepts.

    Cheers,
    Sridevichitthu


Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
About us
Applying for a job can be a stressful and frustrating experience, especially for someone who has never done it before. Considering that you are competing for the position with a at least a dozen other applicants, it is imperative that you thoroughly prepare for the job interview, in order to stand a good chance of getting hired. That's where GeekInterview can help.
Interact