Thread: How To Upgrade QC 10

  1. #1
    Junior Member
    Join Date
    Apr 2009
    Answers
    2

    Unhappy How To Upgrade QC 10

    Hi,

    As We have QC 9.2 and now i want to upgrade it to 10.

    I am the Responsible person for upgrading QC.

    My Manager has given a Target for this.

    Request you to please help me how to start from base.

    Wht shoild i do?

    As i really don't know wht/how to do and whr to start

    Please Help.

    Sunil


  2. #2
    Junior Member
    Join Date
    Apr 2009
    Answers
    2

    Re: How To Upgrade QC 10

    Plz rply to this thred it will be really appriciated


  3. #3

    Re: How To Upgrade QC 10

    Hi sunil, 1. In quality centre v9.2 site admin a. Create a new db server that points to your version 10 database server - i.e. The connection string points to the server where your version 10 database resides b. Create a new domain that will be used to transisition your projects between the two versions 2. In quality centre v10 site admin a. Create a new db server ( on your version 10 box ) that has exactly the same name as the one you created in version 9.2 ( step 1a ) b. Create a new domain that will be used to transisition your projects between the two versions 3. On your version 10 apps server - in windows explorer map the repository directory from version 9.2. This is necessary to be able to find the dbid.xml file for the projects in the transition domain procedure 1. In quality centre v9.2 site admin a. Copy a project into the transisition domain. Select the db server that points to the version 10 db - as created above b. When the copy is complete remove the project from the domain - do not delete 2. In quality centre v10 site admin a. Create the project by clicking on the restore project option and then select the relevant dbid.xml file from the version 9.2 repository. B. Verify, repair, and upgrade the project c. Copy the project from the transition domain to a 'proper' version 10 domain. This is necessary to move the repository off the version 9.2 server and onto the verison 10 server d. Delete the transition project if possible it is better to perform all tasks directly on the app servers of the two versions. Once all copies has been completed then there are clean up tasks. Folders in the qc repository on both versions as well as the upgrade logs on the version 10 server. Thanks, somesh


  4.  Sponsored Ads
    Ad


     

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
About us
Applying for a job can be a stressful and frustrating experience, especially for someone who has never done it before. Considering that you are competing for the position with a at least a dozen other applicants, it is imperative that you thoroughly prepare for the job interview, in order to stand a good chance of getting hired. That's where GeekInterview can help.
Interact