6 men can do a work in one year & 2 months then 3 men can do the same work in how many months?

Showing Answers 1 - 27 of 27 Answers

Senthil

  • Dec 2nd, 2014
 

Less Men, More days(Indirection), so inverse the mens proportion
3:6::14:x
3:x::14X6
x= 84/3 = 28

  Was this answer useful?  Yes

Shehab Khairul

  • Dec 2nd, 2014
 

7 months

  Was this answer useful?  Yes

syam

  • Feb 26th, 2015
 

Shehab, recruit 0 men then, you will get the whole work done in NO time!! :-)

  Was this answer useful?  Yes

Vim

  • Mar 7th, 2015
 

28 months

  Was this answer useful?  Yes

Ritesh Puri

  • Mar 15th, 2015
 

28 months

  Was this answer useful?  Yes

Jahangir Hossain Sheikh

  • Mar 20th, 2015
 

20 months

  Was this answer useful?  Yes

Kumar

  • Apr 3rd, 2015
 

6 men can do in 14 month
1 man can do in 14*6 = 84 months
3 men can do 84/3 = 28 months

  Was this answer useful?  Yes

Ahmad

  • Apr 10th, 2015
 

28 months

  Was this answer useful?  Yes

Dhrasht

  • Apr 19th, 2015
 

28 Months

  Was this answer useful?  Yes