R.C.C. work

how the Ready mix concrete is checked when received at site before using
Asked by: Interview Candidate | Asked on: Sep 21st, 2011
Showing Answers 1 - 3 of 3 Answers
kumaresan

Answered On : Oct 1st, 2011

Temperature Approximate Setting Time (hours)
100oF (38oC) 1-2/3
90oF (32oC) 2-2/3
80oF (27oC) 4
70oF (21oC) 6
60oF (16oC) 8
50oF (10oC) 11
40oF (4oC) 14
30oF (-1oC) 19
20oF (-7oC) Set will not occur
this std.. by using K Slump test we find the temp and we can check the RMC quality...

  
Login to rate this answer.
karthiga

Answered On : Oct 14th, 2011

u didn't answer that how to check the mix of rmc. By slump test we can only able to check the workability.

  
Login to rate this answer.
DB Patra

Answered On : Oct 16th, 2011

Slump check to be done

  
Login to rate this answer.

Give your answer:

If you think the above answer is not correct, Please select a reason and add your answer below.

Related Open Questions

Ads

Connect

twitter fb Linkedin GPlus RSS

Ads

Interview Question

 Ask Interview Question?

 

Latest Questions

Interview & Career Tips

Get invaluable Interview and Career Tips delivered directly to your inbox. Get your news alert set up today, Once you confirm your Email subscription, you will be able to download Job Inteview Questions Ebook . Please contact me if you there is any issue with the download.