Recurring Activities in Waterfall Method

Which of the following are the recurring activities in modified waterfall method
a) Review
b) Final Inspection
c) Requirement traceability
d) Warranty and support

i) A
ii) A,C,D
iii) D
iv) A,B,C
Asked by: sasghosh | Member Since Feb-2009 | Asked on: Feb 17th, 2009

View all questions by sasghosh

Showing Answers 1 - 3 of 3 Answers
ds1164

Answered On : May 31st, 2009

View all answers by ds1164

iv) Review, Final Inspection and Requirement Traceability may occur more than once in waterfall method.

  
Login to rate this answer.
jishuthomas

Answered On : Aug 31st, 2010

View all answers by jishuthomas

Ans: D
In Waterfall Model, the project ends once build is delivered. Only maintainence and support takes place

  
Login to rate this answer.
mkdeshpande

Answered On : Feb 3rd, 2011

View all answers by mkdeshpande

A> Review is recurring, because before you exit from each phase in waterfall you need to review

  
Login to rate this answer.

Give your answer:

If you think the above answer is not correct, Please select a reason and add your answer below.

Related Open Questions

Ads

Connect

twitter fb Linkedin GPlus RSS

Ads

Interview Question

 Ask Interview Question?

 

Latest Questions

Interview & Career Tips

Get invaluable Interview and Career Tips delivered directly to your inbox. Get your news alert set up today, Once you confirm your Email subscription, you will be able to download Job Inteview Questions Ebook . Please contact me if you there is any issue with the download.