GeekInterview.com
  I am new, Sign me up!
 
GeekInterview.com  >  Interview Questions  >  Testing  >  Test Cases
Go To First  |  Previous Question  |  Next Question 
 Test Cases  |  Question 249 of 258    Print  
Effort Varience in QA
What is Effort Varience in QA


  
Total Answers and Comments: 4 Last Update: August 12, 2009     Asked by: sriramt77 
  
 Sponsored Links

 
 Best Rated Answer
Submitted by: Stalin Jesudoss
 

Effort Variance (%) Project effort estimates will be done in terms of man-hours. The Effort Variance would be calculated as below 

Effort Variance = (Actual Effort – Planned Effort) / (Planned Effort) * 100



Above answer was rated as good by the following members:
mahule_n
October 22, 2008 08:10:04   #1  
Stalin Jesudoss Member Since: January 2007   Contribution: 2    

Effort Variance in QA

Effort Variance ( ) Project effort estimates will be done in terms of
man-hours. The Effort Variance would be calculated as below


Effort Variance (Actual Effort Planned Effort) / (Planned Effort) * 100


 
Is this answer useful? Yes | NoAnswer is useful 1   Answer is not useful 0Overall Rating: +1    
November 29, 2008 04:21:44   #2  
srinivasulub1981 Member Since: December 2005   Contribution: 381    

RE: Effort Varience in QA

It's just calculating the extra time spend on testing in our project my client asked the estimates for all types of requirements then we started our testing if QA time is exceeded then we should give a explanation as why it takes the extra time if it's a valid reason there will be no problem other wise problem for entire QA team.

Srinivas


 
Is this answer useful? Yes | No
March 12, 2009 04:34:14   #3  
G.D.S.Prasad Member Since: November 2006   Contribution: 191    

RE: Effort Varience in QA
Effort Variance (Actual Efforts - Planned Effort)/Planned Efforts
In general the Effort Variance Should be in between +/- 5

 
Is this answer useful? Yes | No
August 12, 2009 02:27:04   #4  
mathan_vel Member Since: December 2007   Contribution: 422    

RE: Effort Varience in QA

This metric gives the variation of actual effort vs. the estimated effort. This is calculated for each project Stage wise

Formula

EV [(Actual person hours – Estimated person hours) / Estimated person hours] * 100

Calculated at

Stage completion as identified in SPP

Calculated from

Estimation sheets for estimated values in person hours for each activity within a given stage and Actual Worked Hours values in person hours.



 
Is this answer useful? Yes | No


 
Go To Top


 Sponsored Links

 
About Us -  Privacy Policy -  Terms and Conditions -  Contact -  Ask Question -  Propose Category -  Site Updates 

Copyright © 2005 - 2009 GeekInterview.com. All Rights Reserved

Page copy protected against web site content infringement by Copyscape