GeekInterview.com
   Home |  Tech FAQ  |   Interview Questions |  Placement Papers |  Tech Articles |  Learn |  Freelance Projects |  Online Testing |  Geeks Talk |  Job Postings |  Knowledge Base | Site Search |  Add/Ask Question

GeekInterview.com  >  Placement Papers  >  TCS  >  Aptitude
Go To First  |  Previous Question  |  Next Question 
 Aptitude  |  Question 44 of 147    Print  
3 men finish painting a wall in 8 days. Four boys do the same job in 7 days. In how many days will 2 men and 2 boys working together paint two such walls of the same size?

a) 6 6/13 days

b) 3 3/13 days

c) 9 2/5 days

d) 12 12/13 days

  
Total Answers and Comments: 6 Last Update: February 10, 2008     Asked by: nurankl84 
  
 Sponsored Links

 
 Best Rated Answer
Submitted by: keerthi
 
The ans for this q is 6 6/13

Above answer was rated as good by the following members:
piyush_dnma, atulchowdhary
July 14, 2006 09:48:28   #1  
keerthi        

RE: 3 men finish painting a wall in 8 days. Four boys ...
The ans for this q is 6 6/13
 
Is this answer useful? Yes | NoAnswer is useful 1   Answer is not useful 0Overall Rating: +1    
August 16, 2006 09:47:03   #2  
srinu        

RE: 3 men finish painting a wall in 8 days. Four boys ...
The answer is 6 6/13.
 
Is this answer useful? Yes | NoAnswer is useful 1   Answer is not useful 0Overall Rating: +1    
September 19, 2006 16:28:40   #3  
mandar dindorkar        

RE: 3 men finish painting a wall in 8 days. Four boys ...

3 men -> 8 days

as men decrease => days increase

=> 1 man ->24 days =>1 man's 1 day work = 1/24

4 boys -> 7 days

=> 1 boy ->28 days => 1 boy's 1 day work = 1/28

so 2 men + 2 boys 1 day work = 2/24 + 2/28 = 1/12+ 1/14 = 13/84

so 2men + 2boys finish 13/84 of work in 1 day

so days  to finish total work = 84/13 i.e 6 6/13


 
Is this answer useful? Yes | NoAnswer is useful 2   Answer is not useful 0Overall Rating: +2    
December 27, 2006 07:07:14   #4  
abbs        

RE: 3 men finish painting a wall in 8 days. Four boys ...
The answer is D. We have been asked to calculate days required to paint TWO such walls hence 2*84/13 i.e. 12 12/13 days is the answer.
 
Is this answer useful? Yes | NoAnswer is useful 0   Answer is not useful 1Overall Rating: -1    
September 17, 2007 02:32:06   #5  
Akshaya        

RE: 3 men finish painting a wall in 8 days. Four boys ...
The answer is 3 3/13 .
b coz...
He asks 2men and 2 boys working together to paint 2 walls not for a one wall.

2 men + 2 boys takes 6 6/13 days to paint for a one wall

For 2 walls it will be 3 3/13.

 
Is this answer useful? Yes | No
February 10, 2008 00:50:09   #6  
subhrojitn Member Since: February 2008   Contribution: 2    

RE: 3 men finish painting a wall in 8 days. Four boys do the same job in 7 days. In how many days will 2 men and 2 boys working together paint two such walls of the same size? a) 6 6/13 days b) 3 3/13 days c) 9 2/5 days d) 12 12/13 days
i man can paint 1/24 th part of the wall
i boy paints 1/28 th part

 .
. . 2 boys and 2 men paints 1/12+1/14 th part;13/84 th part in one day
 .
. . to complete one wall they take 84/13 days

 .
. . two walls takes 2*84/13 days
         12
or 12 ---    days
         13

 
Is this answer useful? Yes | No


 
Go To Top


 Sponsored Links

 




About Us  |   Privacy Policy  |   Terms and Conditions  |   Contact  |   Site Map  |   Add Question  |   Propose Category  |   RSS Feeds  |   Articles Sitemap  |   Site Updates  |   Add Resource

Copyright © 2005 - 2008 GeekInterview.com. All Rights Reserved
Page copy protected against web site content infringement by Copyscape