SRS- software Requirement Specifications

BRS- Business Requirement Specifications

  Was this answer useful?  Yes

skumar

  • Jul 12th, 2006
 

SRS: Software Requirements Specification . Srs is prepared by Software Analyst. They implement the BRS iN preparation of Srs.

BRS: Business Requirement Specification. BRS is given by Client . It tells  the business Logics .

EX: hOW TO CALICULATE cOMMISSION AND ON WHICH COMPONENT LIKE TAHT .

  Was this answer useful?  Yes

suresh0249

  • Aug 10th, 2006
 

Ans:

SRS : SRS means software requirement specification. SRS is the analyze document of BRS.

BRS : BRS means business requirement specification. It contains the clients requirement.Depending on BRS business analyst prepare the SRS documents.

  Was this answer useful?  Yes

giri

  • Nov 1st, 2007
 

BRS-- Business requirement specification, it is given by client only(all the client requirements would be there without the proper procedure)

SRS--Software Requirement specification, It specifies the all the requirements of the customer.

             SRS is developed based on BRS only.
                                        
                                             BRS
                                                |
                                             HLD(High Level Design)
                                                |
                                             LLD(Low Level Design)
                                                 |
                                              SRS
Please correct if you find any mistakes.
                                                    

  Was this answer useful?  Yes

BRS- business requirements specification
Business analyst will interact with the client and will form Brs document, it contains

scope of the project,
business rules,
client requirements in depth.

based on BRS system analyst will form Srs document, it contains

system requirements,
functionality to be developed and

what is input
what is output
what is front end
what is back end
what are the technologies
what r processes
how they will interact.

based on srs document design will be generated.

  Was this answer useful?  Yes

snreddy

  • Feb 7th, 2008
 

SRS is a Software /System Requirement specification,it is a MS word doc. which defines the complete business functionalities of the particular application
SRS designed by System Anallyst

BRS is a Business Requirement Specification,Initially client will give the req's in their own format then it will be converted in to Standard format by which s/w people can understand.

In BRS the req's are defined in general format. where as in SRS ,the req's will be divided in to modules and each module contains How many interfaces and screens like that

BRS is developed by Business Analyst 
  

  Was this answer useful?  Yes