End to End Testing: From first smoke test build to release of software to end of maintanence

Complete Cycle of testing: From Reqts to Testing to release of software to end of maintanence

system testing:

Ex: There are 7 modules in project

1+2 = Integration testing

(1+2)+3 = Integration testing

.................................

(1+2...)+..+7= End of Integration testing = System Testing

  Was this answer useful?  Yes

System Testing:This is the process of testing end to end business functionalities of the application(system) based on client business requirements.

End to End Testing:This is the macro end of the testing.This testing mimics the real life situations by interacting with the real time data,  network and harware etc.

In the system testing we are taking sample test data only, where as in the end to end testing we are taking real time data(for a sample) and interacting with network and hardware

withregards

snreddy

  Was this answer useful?  Yes

SATYA DAS

  • Jun 1st, 2006
 

Please tell me some important manual testing interview questions.

  Was this answer useful?  Yes

revathi

  • Jul 19th, 2006
 

pls explain end to end testing with examples

  Was this answer useful?  Yes

sudhakar2068

  • Aug 9th, 2006
 

End to End testing  is performed before release the product to the customer.

system testing: is  process of attempting to demonstrate the program. Is done by testing group before the product is made available to the customer. it tests whether all applications are availabe functionalities modules are there  for application for testing after intergation and unit testing.

sudhakar kolla

ph:09819859346

  Was this answer useful?  Yes

Guest

  • Sep 8th, 2006
 

End to End testing:A test of the ability of a system to transmit data to a receiving system through an intermediary.



System testing:System Testing:-System Testing is a build (.exe) level testing .In system testing we r not consider the internal coding of the application. Only we consider the behavior of the application



Sudhakar kolla

  Was this answer useful?  Yes

shann

  • Sep 28th, 2006
 

System Testing Black-box type testing that is based on overall requirements specifications; covers all combined parts of a system.End-To-End Testing Similar to system testing; the 'macro' end of the test scale; involves testing of a complete application environment in a situation that mimics real-world use

  Was this answer useful?  Yes

Hellow All,

 

The purpose of E2E testing is to ensure that UAT can take place i.e. the application is stable enough for users to concentrate on evaluating business functionality and usability and avoid being sidetracked as a result of running into system bugs and errors

 

This phase entails the connection of the newly delivered application, running on the agreed architecture, utilising the delivered installation and configuration documentation provided by VividOrange, whilst connecting and communicating with all directly interfacing applications and systems.

 

The Integration and Test team will take data fed from incoming interfaces and interfacing systems, process using delivered SmartChange functionality and exported using outbound interfaces. It will ensure that the interfacing applications and systems receive interface data as expected in a format they can process successfully which will not impact the support for that system.

 

This processing may be extended to indirectly interfacing systems where specific risks or concerns exist. This may include the provision of additional interfacing test environments. The precise scope of End to End testing will be finalised during the delivery phase.

 

 

srinivasulu.B (Srinivasulub1981@gmail.com)

  Was this answer useful?  Yes

End to End testing is the final stage of testing done by the end users before relesing product the end users to get confindece on the product(its mainly involves in alpha testign or beta testing)

System testing is the main stage of testing should be done on the AUT and fixes should be done at the same time.System testing carries before End to end testing.

regards
Preethi

  Was this answer useful?  Yes

Give your answer:

If you think the above answer is not correct, Please select a reason and add your answer below.

 

Related Answered Questions

 

Related Open Questions