GeekInterview.com
  I am new, Sign me up!
 
GeekInterview.com  >  Interview Questions  >  Testing  >  Bug Tracking
Go To First  |  Previous Question  |  Next Question 
 Bug Tracking  |  Question 13 of 94    Print  
On what basis the planned testing efforts is calculated for the entire project?

  
Total Answers and Comments: 9 Last Update: March 12, 2009     Asked by: bavithamb 
  
 Sponsored Links

 
 Best Rated Answer

No best answer available. Please pick the good answer available or submit your answer.
January 21, 2006 04:48:22   #1  
Chandrasekar        

RE: On what basis the planned testing efforts is calcu...

The Planned testing efforts can be calculated with 2 different techniques.

1. Function Point Analysis

2. Testing Point Analysis

These methods involves the calculation on the number of functional points present in the application.

I have not performed any analysis but in our company we are following these methods.


 
Is this answer useful? Yes | No
January 28, 2006 02:14:16   #2  
vibha_testing Member Since: December 2005   Contribution: 10    

RE: On what basis the planned testing efforts is calcu...

After completion of test initialization and process finalisation by Project Manager by Quality Analyst Test Lead concentrates on Test Planning to define what to be tested How to be tested and Who to be tested and When to be tested . Test plan is an implementation of Test Methodology selection by Project Manager. In general Test Lead Category people are developing overall plan and multiple test plans for every phase of testing due to different people different techniques different and different environment.

Team Formation Identifying tactical risks preparing system test plan and reveiving the testplan preparaion will be done by TestLead to estimate the completeness of that planned document.


 
Is this answer useful? Yes | No
February 15, 2006 05:14:04   #3  
nitesh484 Member Since: February 2006   Contribution: 56    

RE: On what basis the planned testing efforts is calcu...
I think testing effort is calculated based on Test case if test case also specify complexity . Further schedule / Risk play major role in Testing effort
 
Is this answer useful? Yes | No
March 02, 2006 06:43:58   #4  
Trinadh Bonam        

RE: On what basis the planned testing efforts is calcu...

On what basis the planned testing efforts is calculated for the entire project?

For the entire project or for any release(build) testing effort is calculated based on the items for the project/release and number of test cases that are there and number of people who are going to execute those test cases and the number of testcases a person can execute per a day(man hours) are mainly considered.


 
Is this answer useful? Yes | No
March 05, 2006 02:36:42   #5  
Rakesh        

RE: On what basis the planned testing efforts is calcu...

Hi All

As per my knowledge...

Testing efforts can be planned basing on the system complexity (How big and how much complex is) Number of resources Number of test cases and project dead lines. Initially test plan will be prepared which wil give the tenative plan for the whole testing process.

Thanks


 
Is this answer useful? Yes | No
April 24, 2006 05:36:18   #6  
SCHITTOOR        

RE: On what basis the planned testing efforts is calcu...

This is The cal of test effort:-

Test efficiency (number of tests required / the number of system errors)

Thanks

Srinivasulu.Chittoor

Covansys


 
Is this answer useful? Yes | No
November 10, 2006 04:58:05   #7  
srinivasulub1981 Member Since: December 2005   Contribution: 387    

RE: On what basis the planned testing efforts is calcu...

The testing effort is calculated depends on what type of testing methods ( functional or no functional) customer need to implement and functionality of the the project.. and also depends on team size.. like this on somany ways the testing effort will be calculated.

srinivasulu.B (srinivasulub1981@gmail.com)


 
Is this answer useful? Yes | No
August 23, 2007 18:54:38   #8  
mansi08 Member Since: August 2007   Contribution: 1    

RE: On what basis the planned testing efforts is calcu...
Test Effort is the estimation of the costs of (yet to come) tests. Two ways of calculating the cost are:

1) Functional Point Analysis (FPA) - This is an ISO recognized method to calculate the number of functions present in the system. Depending on the functions required number of tests can be estimated. This method covers White-box testing estimation only.


2) Test Point Analysis (TPA) - This is another method to estimate black box testing costs ie the System Testing and UAT. TPA depends upon the size of the project test strategy and productivity.


 
Is this answer useful? Yes | No
March 12, 2009 02:51:57   #9  
G.D.S.Prasad Member Since: November 2006   Contribution: 191    

RE: On what basis the planned testing efforts is calculated for the entire project?

We follow TCP analysis to calculate the testing effort required for a change
request. Some organizations follow FTP Analysis.


Test Case Points (TCP) Test Case Point deals with the estimation of
the effort needed for testing projects. It is technology independent & supports
the need for estimating project management & measuring quality. This approach
enables separate effort estimates for different phases of testing viz. Test Case
Generation Automated Test Cases & Test Case Execution.


Function Test Points (FTP) It estimates size & efforts for testing
activities. Each test requirement is decomposed into possible atomic logical
functions & mapped them with complexity factor.


 
Is this answer useful? Yes | No


 
Go To Top


 Sponsored Links

 
About Us -  Privacy Policy -  Terms and Conditions -  Contact -  Ask Question -  Propose Category -  Site Updates 

Copyright © 2005 - 2009 GeekInterview.com. All Rights Reserved

Page copy protected against web site content infringement by Copyscape