GeekInterview.com
  I am new, Sign me up!
 
GeekInterview.com  >  Interview Questions  >  Testing  >  Testing Scenarios
Go To First  |  Previous Question  |  Next Question 
 Testing Scenarios  |  Question 10 of 35    Print  
other than requirement traceability matrix what all other factors that we need to check in order to exit a testing process

  
Total Answers and Comments: 7 Last Update: May 06, 2009     Asked by: md_shamiullah 
  
 Sponsored Links

 
 Best Rated Answer
Submitted by: tinkle
 

To Exit the testing process we need to consider following :-

  1. The number of sev 1 defects
  2. Need to check whether the Quality measures defined in the test Plan are all met?
  3. Need to consider Mean time between failures
  4. The Test budget
  5. The project deadline (Importance of product to the client)
  6. The business risk of releasing/not releasing the software to the users

Thanks & regards

Tinkle



Above answer was rated as good by the following members:
vk1978
December 19, 2005 11:58:37   #1  
venkatraog Member Since: December 2005   Contribution: 3    

RE: other than requirement traceability matrix what al...
i think it is enough to proceed testing.
 
Is this answer useful? Yes | No
January 31, 2006 00:48:35   #2  
tinkle        

RE: other than requirement traceability matrix what al...

To Exit the testing process we need to consider following :-

  1. The number of sev 1 defects
  2. Need to check whether the Quality measures defined in the test Plan are all met?
  3. Need to consider Mean time between failures
  4. The Test budget
  5. The project deadline (Importance of product to the client)
  6. The business risk of releasing/not releasing the software to the users

Thanks & regards

Tinkle


 
Is this answer useful? Yes | NoAnswer is useful 1   Answer is not useful 0Overall Rating: +1    
April 14, 2006 01:34:28   #3  
M.Ragothaman        

RE: other than requirement traceability matrix what al...

1. All bugs are addressed

2. Testing Budget

3. Delivery of project

Raghu


 
Is this answer useful? Yes | No
November 13, 2006 10:15:19   #4  
Pradeep R        

RE: other than requirement traceability matrix what al...

To stop testing these are the main factors.

1. Reduce in defects.

2. Increase in Testing cost.

3. Delivary dates.

Pradeep r


 
Is this answer useful? Yes | No
May 25, 2007 05:58:47   #5  
parashersudhakar Member Since: May 2007   Contribution: 6    

RE: other than requirement traceability matrix what al...
Other than Tracebility Matrix:

We need to check that

1) Whether all the Bugs which were Assigned to developers have been fixed .
2) All the documents pertaining to testing have been prepared.
3) all the bugs which were in Previous releases have been retested .

Br//
Sudhakar

 
Is this answer useful? Yes | No
July 15, 2007 23:20:07   #6  
Brahma        

RE: other than requirement traceability matrix what al...
1. software test coverage document
2. functional coverage document


 
Is this answer useful? Yes | No
May 06, 2009 06:22:29   #7  
srinivasulub1981 Member Since: December 2005   Contribution: 381    

RE: other than requirement traceability matrix what all other factors that we need to check in order to exit a testing process
Hi


As all of us knows that there is no end for testing but we can stop testing if any of the below points crossed.


-> Bug ratio is coming down as per the company standards

-> Schedule crossed

-> High sev issues were closed.


Thanks
Srinivas

 
Is this answer useful? Yes | No


 
Go To Top


 Sponsored Links

 
About Us -  Privacy Policy -  Terms and Conditions -  Contact -  Ask Question -  Propose Category -  Site Updates 

Copyright © 2005 - 2009 GeekInterview.com. All Rights Reserved

Page copy protected against web site content infringement by Copyscape