Question: Recurring Activities in Waterfall Method
Answer: Which of the following are the recurring activities in modified waterfall method a)
Review
b) Final Inspection
c) Requirement traceability
d) Warranty and support
i) A
ii) A,C,D
iii) D
iv) A,B,C |
| May 05, 2009 11:17:36 |
#1 |
| ds1164 |
Member Since: May 2009 Total Comments: 4 |
RE: Recurring Activities in Waterfall Method |
| iv) Review, Final Inspection and Requirement Traceability may occur more than once in waterfall method. |
| |