RE: Assign Task to Testers |
| Task assignment is usually given by the Project Manager. Your Business Analyst or testing group would be responsible for creating test cases in detail. There should be test environments established and a change management process (if there isn't one your Business Analyst should be able to work with the team to define and document a good Change Management process) defined with a bug tracking tool to be used. To make testers accountable you could create a spreadsheet of the detail you would like tracked and send it to the testers requesting a daily or weekly status of their findings. Then arrange for a daily or weekly meeting to resolve bugs/issues and track when those items are fixed as a collaborative effort between your testing and development teams (this is a manual process so you should expect to see duplicate bugs/issues between team member's submittals). |
| |